CAPACITY EVALUATION

CAPACITY EVALUATION

G.I. DUCT

Straight Duct

Automatic Coil Line (24G to 18G) Duct Size 400mm X 400mm 5 Tons/Shift
Monthly Capacity based on 26 days / Month 130Tons/Month

Duct

Plasma Sheet Cutting Capactiy 150 Nos/Shift
Total per month based on 26 days/month (Based on two shifts) 7800Nos/Month

Sheet Size

Sheet Sq. Mtr. 3M x 1.22 M
Sheet Weight (22G) 3.66 Sq. Mtr.
Deduction of Wastage (10%) 20.12 Kg
Total Production of Fittings per Month 18.1 Kg
Fabrication Capacity: 282 Tons/month
(Based on 40% Straight & 60% Fitting Ratio & Double Shift) 252 Tons/month

RIP DUCT

PIR Duct

CNC SABRECUT 4000 MACHINE 360 SQM/DAY
Monthly Capacity based on 26 days/month 9360 SQM/Month
Sheet Size 4M x 1.22 M
Sheet Sq. Mtr. 4.80 Sq. Mtr.
Sheet Thickness 20MM & 30MM
Deduction of Wastage (10%) 36 SQM x 26 = 936 SQM
Fabrication Capacity: 8,424 SQM in Month