Current activities

Pre-Engineering has been Completed

Detailed Engineering to be started

Environmental Impact Assessment (EIA) pre-study Completed. Consequence Analysis (including EIA) Completed by Scandpower. This analysis is per Norwegian rules and regulations and will be submitted to Norwegian Climate and Pollution Agency

Life Cycle Analysis for the project Completed by MiSA

Project Site office established 2019

Logistics planning of Caustic Soda and CO2 from Local UAE to market is ongoing. Sourcing of further back-up sources is on-going.

The distribution company will purchase all products FOB at documented European prices and coordinate all logistics from the plant.